Note • Advice and Advocacy

EO 14402 Makes Fixed-Price Contracts the Default Contract Type

Executive Order 14402, signed April 30, 2026, directs executive branch departments and agencies to utilize fixed-price contracts as the default contract type. and requires them to identify and restructure their largest non-FFP contracts by late July — a structural shift with significant consequences for government contractors.

Executive Order 14402, titled “Promoting Efficiency, Accountability, and Performance in Federal Contracting,” establishes firm-fixed-price contracts, as defined in Part 16 of the Federal Acquisition Regulation, as the government-wide default. Use of cost-reimbursement, time-and-material, or other non-FFP contract types above agency-specific dollar thresholds requires written justification from the contracting officer to the agency head. That approval requirement is not a formality — it is intended to advance cost predictability and budget discipline, encourage appropriate contractor incentives and accountability, and streamline procurement and contract administration.

The near-term deadline that matters most is July 29, 2026. By that date, executive branch departments and agencies must identify their ten largest non-fixed-price contracts and actively seek to modify, restructure, or renegotiate them. Certain categories are exempt from the order, including contracts supporting emergency response, major disaster relief, contingency operations, and research-and-development or pre-production development of major systems. But outside those exemptions, the sweep is wide.

Contractors holding cost-reimbursement contracts face the most direct exposure. These instruments have been the standard vehicle for complex development, systems engineering, and research work precisely because the scope cannot be fully defined in advance. The pricing logic of cost-type contracting — incurred costs plus fee — is fundamentally incompatible with firm-fixed-price mechanics. When the government pushes a cost-type scope into a fixed-price structure without adjusting the technical requirements or the performance baseline, the contractor absorbs all cost overrun risk on work that may not be fully defined.

The Risk Profile for Cost-Type Contractors

That change affects risk allocation. For contractors facing agency-initiated restructuring of existing non-FFP contracts, the leverage dynamics in those negotiations will depend heavily on whether the agency genuinely needs to convert the contract type or is responding to top-down pressure without a clear technical rationale for doing so.

Pricing and REA Implications

The shift to FFP does not eliminate unforeseen conditions or government-caused changes — it changes who bears them initially and how recovery is framed. On a firm-fixed-price contract, a contractor encountering government-caused disruption, scope growth, or defective specifications must pursue recovery through a Request for Equitable Adjustment or a CDA claim. That path exists under FAR and case law, but it requires documentation, contemporaneous records, and proactive claim submission discipline that some contractors accustomed to cost-type practice may not have maintained as rigorously.

Contractors engaged in restructuring discussions should be especially attentive to how the conversion proposal defines the baseline. A fixed price negotiated on an overly optimistic performance baseline — or one that omits risks that should be government-borne — is a recipe for dispute. If the agency is proposing to convert a major non-FFP contract under the July 29 mandate, that negotiation deserves the same scrutiny as a new contract award. The conversion document is the contract, and its pricing assumptions, risk allocation provisions, and change-order mechanisms will control the relationship going forward.

For new solicitations, the landscape is shifting immediately. Expect agencies to default to FFP structures in areas where cost-type has historically been the norm, and expect contracting officers to document the agency-head justification when they do deviate. That documentation may itself become a discovery target in future disputes if the agency later argues that cost overruns are the contractor’s problem.

The exemption categories deserve attention. R&D and pre-production development of major systems are excluded from the fixed-price default, which means the order’s most immediate impact falls on the large volume of cost-type service, support, and sustainment contracts that do not qualify for those exemptions. Contractors in defense IT, logistics, facilities, and professional services who have been working under cost-type arrangements should expect contracting officers to approach renewals and follow-ons under the new framework even when the requirement’s technical uncertainty has not changed. The burden is now on the agency to justify any departure from FFP, and contracting officers operating under institutional pressure to comply with the EO’s mandate may prefer the path of least bureaucratic resistance — which is a fixed-price structure regardless of technical fit.

Takeaways

  • Identify all active cost-reimbursement, T&M, and non-FFP contracts now; those above applicable agency thresholds are candidates for agency-initiated restructuring before July 29, 2026.
  • Treat any EO-driven contract conversion as a negotiation requiring technical and pricing due diligence — the conversion baseline and risk allocation provisions are not administrative formalities.
  • For new solicitations, evaluate whether an FFP structure is technically appropriate for the requirement and whether the solicitation’s performance baseline supports that structure before committing to a price.
  • On converted FFP contracts, invest immediately in the documentation disciplines — change logs, contemporaneous impact records, REA tracking — that cost-type practice often allowed to be less rigorous.
  • Confirm whether the contract falls within an exemption (R&D, pre-production, emergency response) before assuming restructuring is mandatory.

Sources

Executive Order 14402, Promoting Efficiency, Accountability, and Performance in Federal Contracting, 91 Fed. Reg. 24325 (April 30, 2026).